# The Transport for Greater Manchester (Light Rapid Transit System) (Trafford Park Extension) Order 2016, Paragraph 14: Removal of apparatus


If the undertaker gives notice in writing to the public utility that it desires to carry out any part of any work in connection with the construction or removal of apparatus, such work, instead of being carried out by the public utility, may be carried out by the undertaker with the prior written consent of the public utility (which must not be unreasonably withheld and may be subject to any such conditions as are reasonable and proper to protect the apparatus) in accordance with plans and in a position agreed between the public utility and the undertaker or, in default of agreement, determined by arbitration under article 53 (arbitration), without unnecessary delay under the superintendence (if given) and to the reasonable satisfaction of the public utility.

---
Source: https://www.legislation.gov.uk/uksi/2016/1035/schedule/8/paragraph/14 (the official version)
Page: https://openlegislation.uk/transport-for-greater-manchester-light-rapid-transit-system-trafford-park-extension-order-2016/schedule-8/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

