Paragraph 8 Removal of apparatus
Paragraphs 9 to 16 apply where—
(a)
the undertaker requires the removal of any apparatus for the purpose of constructing any of the authorised works and gives to the public utility not less than 56 days’ written notice of that requirement together with a plan of the proposed work and of the proposed position of the necessary alternative apparatus to be provided or constructed; or
(b)
in consequence of the exercise or proposed exercise of any of the powers conferred by this Order, the public utility reasonably requires the removal of any apparatus.