# The Transport for Greater Manchester (Light Rapid Transit System) (Trafford Park Extension) Order 2016, Paragraph 3


Where reasonably required to do so by the engineer or the harbour master for the purpose of ensuring the safety of the Canal the undertaker must, to the reasonable satisfaction of the engineer or harbour master, fence off any specified work or protective work or take such steps as the engineer or the harbour master may reasonably require to be taken for the purpose of separating a specified work or a protective work from the Canal, whether on a temporary or permanent basis or both.

---
Source: https://www.legislation.gov.uk/uksi/2016/1035/schedule/9/paragraph/3 (the official version)