# The Triton Knoll Electrical System Order 2016, Paragraph 1: Interpretation

Extent: E+W+S

In this Part—
“above-ground infrastructure” means the buildings, busbars, capacitors, reactors, reactive power compensation equipment, filters, cooling equipment, control and welfare buildings, lightning rods, security fencing and other associated equipment, structures and buildings including noise-attenuation panels required for the intermediate electrical compound and the substation compound (Work No. 50A);
“AIS” means air-insulated switchgear;
“AOD” means above ordnance datum;
“GIS” means gas-insulated switchgear;
“stage” means one of the following 28 stages of the onshore works—
(a) the IEC enabling works (using the temporary construction compound at Work No. 10);
(b) the substation enabling works (using the temporary construction compound at Work No. 51);
(c) Work Nos. 3 and 4 including Work Nos. 3A and 3B (using the temporary construction compound at Work No. 3B);
(d) Work No. 5 (using the temporary construction compound at Work No. 6);
(e) Work No. 8 (using the temporary construction compound at Work No. 7);
(f) Work No. 9 excluding the IEC enabling works and Work No. 9A (using the temporary construction compound at Work No. 10);
(g) Work No. 9A (using the temporary construction compound at Work No. 10);
(h) Work No. 11 (using the temporary construction compound at Work No. 12);
(i) Work No. 14 (using the temporary construction compounds at Work Nos. 13 and 15);
(j) Work No. 17 (using the access at Work No. 16);
(k) Work No. 19 (using the temporary construction compound at Work No. 18);
(l) Work No. 21 (using the temporary construction compound at Work No. 20);
(m) Work No. 22 (using the temporary construction compound at Work No. 23);
(n) Work No. 24 (using the temporary construction compound at Work No. 25);
(o) Work No. 26 (using the temporary construction compounds at Work Nos. 27 and 28);
(p) Work No. 29 (using the temporary construction compound at Work No. 30);
(q) Work No. 31 (using the temporary construction compound at Work No. 32);
(r) Work No. 33 (using the temporary construction compounds at Work Nos. 34, 35 and 36);
(s) Work No. 37 (using the temporary construction compound at Work No. 38);
(t) Work No. 39 (using the temporary construction compounds at Work Nos. 40 and 41);
(u) Work No. 42 (using the temporary construction compound at Work No. 43);
(v) Work No. 44 (using the temporary construction compound at Work No. 45);
(w) Work No. 46 (using the temporary construction compound at Work No. 47A or 51 and access at Work No. 48);
(x) Work Nos. 48 and 49 (using the temporary construction compound at Work No. 47A);
(y) Work No. 50 excluding the substation enabling works and Work No. 50A (using the temporary construction compound at Work No. 51);
(z) Work No. 50A (using the temporary construction compound at Work No. 51);
(aa) Work No. 52 (using the temporary construction compound at Work No. 53);
(ab) Work No. 55 (using the temporary construction compound at Work No. 53),
or such other stage of the onshore works agreed in writing with the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2016/880/schedule/1/part/3/paragraph/1 (the official version)
Page: https://openlegislation.uk/triton-knoll-electrical-system-order-2016/schedule-1/part-3/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.