# The Triton Knoll Electrical System Order 2016, Schedule 7: Land of which temporary possession may be taken

Extent: E+W+S

(1)
District
(2)
Number of land shown on land plans
(3)
Purpose for which temporary possession may be taken
(4)
Relevant part of authorised project
East Lindsey
01/04
Construction and storage compound
Work No. 3B
East Lindsey
05/17, 05/18
Construction and storage compound
Work No. 6
East Lindsey
05/19, 05/20
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks, improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 6
East Lindsey
05/22, 05/23, 05/24, 05/25
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks, improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 7
East Lindsey
05/26, 05/27, 05/28, 05/29
Construction and storage compound
Work No. 7
East Lindsey
10/10
Construction and storage compound
Work No. 10
East Lindsey
13/03, 13/04, 13/05
Construction and storage compound
Work No. 12
East Lindsey
13/06
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 12
East Lindsey
13/08, 13/26
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 13
East Lindsey
13/10
Construction and storage compound
Work No. 13
East Lindsey
18/06
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
(c) Construction and storage compound
Work No. 15
East Lindsey
18/09, 18/10, 18/11
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 16
East Lindsey
18/20
Construction and storage compound
Work No. 18
East Lindsey
19/03
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 18
East Lindsey
20/11, 20/12, 20/14
Construction and storage compound
Work No. 20
East Lindsey
20/13
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 20
East Lindsey
26/04, 26/05,
Construction and storage compound
Work No. 23
East Lindsey
26/08
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 23
East Lindsey
27/02
Construction and storage compound
Work No. 25
East Lindsey
27/05
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 25
East Lindsey
29/10, 29/11,
Construction and storage compound
Work No. 27
East Lindsey
29/13
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 27
East Lindsey
29/16
Construction and storage compound
Work No. 28
East Lindsey
29/15
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 28
East Lindsey
31/12
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
(c) Construction and storage compound
Work No. 30
East Lindsey
33/03
Construction and storage compound
Work No. 32
East Lindsey
36/02, 36/03
Construction and storage compound
Work No. 34
East Lindsey
37/03, 37/04, 37/05
Construction and storage compound
Work No. 35
East Lindsey
37/07 37/08, 37/10
Construction and storage compound
Work No. 36
Boston
39/04
Construction and storage compound
Work No. 38
Boston
39/05
(a) Access with or without vehicles. plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 38
Boston
40/05
Construction and storage compound
Work No. 40
Boston
41/05, 41/06, 41/07
Construction and storage compound
Work No. 41
Boston
41/04
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 41
Boston
43/03
Construction and storage compound
Work No. 43
Boston
43/05
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 43
Boston
43/06
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 45
Boston
43/07
Construction and storage compound
Work No.45
Boston
44/03b
Construction and storage compound
Work No. 47A
Boston
44/04
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work Nos. 47A, 48 and 49
Boston
44/01
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 49
Boston
45/04, 45/05, 45/07, 45/08, 45/10, 45/11, 45/13, 46/04, 46/07
(a) Access with or without vehicles, plant, machinery, apparatus, equipment and materials for construction and carrying out of the authorised project
(b) Laying and use of temporary vehicular access tracks and improvement to access tracks and roads, and erection of associated temporary structures including fencing and signage
Work No. 49
Boston
47/07, 47/08
Construction and storage compound
Work No. 51

---
Source: https://www.legislation.gov.uk/uksi/2016/880/schedule/7 (the official version)
Page: https://openlegislation.uk/triton-knoll-electrical-system-order-2016/schedule-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.