  "url": "https://openlegislation.uk/triton-knoll-electrical-system-order-2016/schedule-8/paragraph-21",
  "json_url": "https://openlegislation.uk/triton-knoll-electrical-system-order-2016/schedule-8/paragraph-21.json",
  "legislation": "uksi/2016/880",
  "legislation_title": "The Triton Knoll Electrical System Order 2016",
  "legislation_url": "https://openlegislation.uk/triton-knoll-electrical-system-order-2016",
  "path": "schedule/8/paragraph/21",
  "kind": "paragraph",
  "number": "21",
  "heading": null,
  "text": "The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 35 (certification of plans, etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in the form of a computer disc with read-only memory.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 8 para. 21 in force at 27.9.2016, see art. 1(2)"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2016/880/schedule/8/paragraph/21",
    "retrieved_at": "2026-10-28T23:20:26.172707+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}