# The Triton Knoll Electrical System Order 2016, Paragraph 6: Force majeure

Extent: E+W+S

(1) If, due to stress of weather or any other cause, the master of a vessel determines that it is necessary to deposit the authorised deposits otherwise than in accordance with this licence because the safety of human life or of the vessel is threatened, full details of the circumstances of the deposit must be notified to the MMO within 48 hours.
(2) The unauthorised deposits must be removed at the expense of the undertaker unless written approval is obtained from the MMO.

---