# The Triton Knoll Offshore Wind Farm Order 2013, Paragraph 10: Pre-construction plans and documentation

Extent: E+W+S

(1) Each programme, statement, plan, protocol or scheme required to be approved under condition 9 shall be submitted for approval at least four months prior to the intended start of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.
(2) The licensed activities shall be carried out in accordance with the approved plans, protocols, statements, schemes and details approved under condition 9, unless otherwise agreed in writing by the MMO.
(3) No part of this licence authorises any part of the authorised scheme extending beyond the detailed design parameters at conditions 1 to 5.

---
Source: https://www.legislation.gov.uk/uksi/2013/1734/schedule/2/paragraph/10 (the official version)
Page: https://openlegislation.uk/triton-knoll-offshore-wind-farm-order-2013/schedule-2/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.