# The Triton Knoll Offshore Wind Farm Order 2013, Paragraph 16: Herring spawning

Extent: E+W+S

No pile driving works shall be carried out by or on behalf of the undertaker as part of or in relation to the authorised scheme between 1st September and 16th October each year unless the MMO provides written confirmation to the undertaker beforehand that such works can take place, in all or in a specified part of the site, during this period or a part of this period.

---
Source: https://www.legislation.gov.uk/uksi/2013/1734/schedule/2/paragraph/16 (the official version)