The Traffic Management (The Metropolitan Borough Council of Stockport) Permit Scheme Order 2013

S.I. 2013/805 · Made 28 March 2013

Original text. legislation.gov.uk does not revise statutory instruments, so later amendments are not shown here. Changes made to it are listed under each provision when known.

Highways, England

Made 28th March 2013

Coming into force 29th April 2013

The Secretary of State for Transport having approved the Metropolitan Borough Council of Stockport Permit Scheme under section 34(2) of the Traffic Management Act 2004f1 makes this Order in exercise of the powers conferred by sections 34(4) and (5) and 39(2) of that Act.

Annotations to the whole text

Footnotes

f1

2004. c.18.

Contents

  1. 1Citation and commencement
  2. 2Interpretation
  3. 3Commencement of Permit Scheme
  4. 4Application of Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007
  5. Signature
  6. Schedule THE METROPOLITAN BOROUGH COUNCIL OF STOCKPORT PERMIT SCHEME
  7. Explanatory note

1Citation and commencement

This Order may be cited as the Traffic Management (The Metropolitan Borough Council of Stockport) Permit Scheme Order 2013 and comes into force on 29th April 2013.

2Interpretation

In this Order—

  • “the Metropolitan Borough Council of Stockport Permit Scheme ” means the permit scheme set out in the Schedule to this Order in terms commonly known as the “Greater Manchester Permit Scheme” which was prepared and submitted to the Secretary of State by The Metropolitan Borough Council of Stockport and has been approved by the Secretary of State; and

  • “specified streets” has the meaning given by regulation 8 of the Traffic Management Permit Scheme (England) Regulations 2007f1.

3Commencement of Permit Scheme

The Metropolitan Borough Council of Stockport Permit Scheme comes into effect on 29th April 2013.

4Application of Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007

Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007 shall apply to the specified streets within the Metropolitan Borough Council of Stockport Permit Scheme.

Signature

Signed by authority of the Secretary of State for Transport

Norman Baker

Parliamentary Under Secretary of State

Department for Transport

28th March 2013

THE METROPOLITAN BOROUGH COUNCIL OF STOCKPORT PERMIT SCHEME

Explanatory note

(This note is not part of the Order)

This Order gives effect to the Metropolitan Borough Council of Stockport Permit Scheme.

The Metropolitan Borough Council of Stockport Permit Scheme is designed to control the carrying out of works in specified streets in Stockport by imposing an obligation to obtain a permit from the Metropolitan Borough Council of Stockport before undertaking the works.

Article 3 gives effect to the permit scheme, which will come into effect on 29th April 2013. The permit scheme referred to in this article is set out in the Schedule to the Order.

Article 4 applies Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007 (which makes provision for the disapplication and modification of enactments in relation to specified works in specified streets) to the specified works and specified streets within the Metropolitan Borough Council of Stockport Permit Scheme.

A copy of the Metropolitan Borough Council of Stockport Permit Scheme is deposited and can be inspected at the offices of The Metropolitan Borough Council of Stockport, Town Hall, Edward Street, Stockport, SK1 3XB and is available to inspect on the Council’s website http://www.stockport.gov.uk.