Regulation 77 Delivery of conversion certificate to registrar of companies
(1)
The company shall deliver to the registrar of companies for registration a certified copy of the certificate signed under regulation 75(1) by which conversion of any security was effected, within 7 working days of the date on which it was signed.
(2)
Section 380(6) of the 1985 Act applies to a failure to comply with the provisions of this regulation as it does to a failure to comply with section 380(2) or (3) of that Act.
(3)
In this regulation “certified copy” means a copy certified as a true copy by a notary, notary public or other person authorised by law, in the jurisdiction where the company is incorporated, to administer oaths or authenticate documents.