# The Value Added Tax (Do-It-Yourself Builders) (Refund of Tax) Regulations 1989, Regulation 3: Method and time for making claim


A claimant shall make his claim in respect of a relevant building by–
(a) furnishing to the Commissioners no later than three months after the completion of the building a prescribed form containing the full particulars required therein; and
(b) unless the Commissioners otherwise allow, at the same time furnish to them–
(i) a certificate of completion obtained from a local authority or such other documentary evidence of completion of the building as is satisfactory to the Commissioners;
(ii) an invoice showing the registration number of the person supplying the goods, whether or not such an invoice is a tax invoice, in respect of each supply of goods on which tax has been paid which have been incorporated into the building or its site;
(iii) in respect of imported goods which have been incorporated into the building or its site, documentary evidence of their importation and of the tax paid thereon;
(iv) documentary evidence that planning permission for the building had been granted; and
(v) a certificate signed by a quantity surveyor or architect, that the goods shown in the claim were or, in his judgment, were likely to have been, incorporated into the building or its site.

---
Source: https://www.legislation.gov.uk/uksi/1989/2259/regulation/3 (the official version)