# The Viking CCS Carbon Dioxide Pipeline Order 2025, Paragraph 3: Stages of authorised development

Extent: E+W

(1) The authorised development must not commence until a written scheme setting out all stages of the authorised development and including a plan indicating when each stage will be constructed has been submitted to each relevant planning authority, which scheme may subsequently be amended from time to time as notified to the relevant planning authority.
(2) The written scheme must be implemented as notified under sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2025/509/schedule/2/paragraph/3 (the official version)
Page: https://openlegislation.uk/viking-ccs-carbon-dioxide-pipeline-order-2025/schedule-2/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.