# The Viking CCS Carbon Dioxide Pipeline Order 2025, Paragraph 6: Construction traffic

Extent: E+W

(1) No stage of the authorised development may commence until a CTMP for that stage, in accordance with the outline construction traffic management plan, has been submitted to and approved by the relevant planning authority and, in respect of effects on the strategic road network, National Highways following consultation with the relevant highway authority and Network Rail.
(2) The CTMP for each stage must include a construction worker travel plan in accordance with the interim worker travel plan and include measures to be taken to promote sustainable travel options and minimise use of private vehicles.
(3) Each stage of the authorised development must be implemented in accordance with the approved CTMP for that stage.

---
Source: https://www.legislation.gov.uk/uksi/2025/509/schedule/2/paragraph/6 (the official version)
Page: https://openlegislation.uk/viking-ccs-carbon-dioxide-pipeline-order-2025/schedule-2/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.