(1) No development of Work Nos 1, 14, 21, 31 or 44 may commence until, for that Work No, a surface water drainage plan for permanent works relevant to that stage, in accordance with the relevant part of the outline surface water drainage strategy, has been submitted to and approved by the relevant planning authority following consultation with Anglian Water.
(2) The surface water drainage system for each stage must be implemented in accordance with the approved details.

---