# The Viking CCS Carbon Dioxide Pipeline Order 2025, Part 1: New permanent means of access from the public highway

Extent: E+W

(1) Area
(2) Street
(3) Description of relevant part of access
In the borough of North East Lincolnshire
Rosper Road
Works for the installation and maintenance of a new access to Work No. 1 at either Point 1-AA or Point 1-AB as shown on sheet 1 of the access and rights of way plans.
In the borough of North East Lincolnshire
Washingdales Lane
Works for the installation and maintenance of a new access to Work No. 14, point 10-AB as shown on sheet 10 of the access and rights of way plans.
In the borough of North East Lincolnshire
Thoroughfare
Works for the installation and maintenance of a new access to Work No. 21, point 16-AB as shown on sheet 16 of the access and rights of way plans.
In the district of East Lindsey
Louth Road
Works for the installation and maintenance of a new access to Work No. 31, point 25-AA as shown on sheet 26 of the access and rights of way plans.

---
Source: https://www.legislation.gov.uk/uksi/2025/509/schedule/4/part/1 (the official version)