# The Viking CCS Carbon Dioxide Pipeline Order 2025, Schedule 6: Land of which only temporary possession may be taken

Extent: E+W

(1) Area
(2) Number of plot shown on land plans
(3) Purpose for which temporary possession may be taken
(4) Relevant part of authorised development
In the borough of North Lincolnshire
1/57
Temporary use as a working area
Work No.01A
In the borough of North East Lincolnshire
4/1, 4/2, 4/3, 4/4, 4/5, 4/6, 4/7, 4/8, 4/9, 4/10, 4/11, 4/12, 4/13, 4/14, 4/15
Temporary use as a construction compound and working area.
Work Nos.7, 7A, 7B
In the borough of North East Lincolnshire
6/1, 6/2
Temporary use as a construction access.
Work No. 9A
In the county of Lincolnshire
9/1, 9/3, 9/6
Temporary use as a construction access.
Work No. 12A
In the borough of North East Lincolnshire
9/13
Temporary use as a construction access.
Work No. 12B
In the borough of North East Lincolnshire
12/6, 12/8
Temporary use as a construction compound and working area.
Work Nos. 16B, 16C
In the borough of North East Lincolnshire
13/6
Temporary use as a construction access.
Work No. 17B
In the borough of North East Lincolnshire
14/3, 14/4, 14/5
Temporary use as a construction access.
Work No. 18A
In the borough of North East Lincolnshire
16/9
Temporary use as a construction access.
Work No. 21C
In the county of Lincolnshire
20/6, 20/7, 20/9
Temporary use as a construction access.
Work No. 25A
In the county of Lincolnshire
20/10, 20/11, 20/13, 20/14
Temporary use as a construction access.
Work No. 25B
In the county of Lincolnshire
24/4, 24/5
Temporary use as a construction access.
Work No. 29A
In the county of Lincolnshire
24/6, 24/7
Temporary use as a construction access.
Work No. 29B
In the county of Lincolnshire
28/7, 28/9, 28/10,28/11
Temporary use as a construction access.
Work No. 34B
In the county of Lincolnshire
29/3, 29/4, 29/5, 29/7
Temporary use as a construction access.
Work No. 34C
In the county of Lincolnshire
30/3, 30/4, 30/5
Temporary use as a construction access.
Work No. 36A
In the county of Lincolnshire
30/13,30/14, 30/15
Temporary use as a construction access.
Work No. 36D
In the county of Lincolnshire
35/2, 35/3, 35/4, 35/6
Temporary use as a construction access.
Work No. 41A
In the county of Lincolnshire
35/42, 36/1
Temporary use as a construction compound and working area.
Work No.47
In the county of Lincolnshire
36/9, 36/10
Temporary use as a working area.
Work Nos. 48C and 48D

---
Source: https://www.legislation.gov.uk/uksi/2025/509/schedule/6 (the official version)
Page: https://openlegislation.uk/viking-ccs-carbon-dioxide-pipeline-order-2025/schedule-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.