# The Viking CCS Carbon Dioxide Pipeline Order 2025, Paragraph 101

Extent: E+W

Regardless of any provision in the Order or anything shown on the land plans or contained in the book of reference, the undertaker must not acquire any apparatus or override any easement or other interest of Northern Powergrid or acquire any other interest of Northern Powergrid or create any new rights over the same otherwise than by agreement of Northern Powergrid such agreement not to be unreasonably withheld or delayed (having regard to Northern Powergrid’s existing and known future requirements for such land or interests).

---