# The Viking CCS Carbon Dioxide Pipeline Order 2025, Paragraph 149: Further provisions about works

Extent: E+W

(1) Before carrying out a relevant work the undertaker must—
(a) provide P66 with baseline data for any existing cathodic protection of the affected asset; and
(b) carry out a pipeline settlement and stress analysis to demonstrate any potential pipeline movement will not present an integrity risk to the affected asset.
(2) A minimum clearance of 1500 millimetres must be maintained between any part of the authorised development and any affected asset unless otherwise agreed with P66.

---