# The Viking CCS Carbon Dioxide Pipeline Order 2025, Paragraph 165: Authorisation of works details affecting pipelines or protected crossings

Extent: E+W

Before commencing any part of a relevant work the undertaker must submit the works details to the IOT Operators and any other information that the IOT Operators may reasonably require to allow it to assess the works.

---
Source: https://www.legislation.gov.uk/uksi/2025/509/schedule/9/paragraph/165 (the official version)