# The Viking CCS Carbon Dioxide Pipeline Order 2025, Paragraph 46: Notices

Extent: E+W

Notwithstanding article 45 (service of notices), any plans submitted to National Gas by the undertaker pursuant to this Part must be submitted to https://lsbud.co.uk/ or such other address as National Gas may from time to time appoint instead for that purpose and notify to the undertaker in writing.

---
Source: https://www.legislation.gov.uk/uksi/2025/509/schedule/9/paragraph/46 (the official version)