Introductory text
Infrastructure Planning
Made 27th July 2016
Coming into force 28th July 2016
An application has been made to the Secretary of State under paragraph 2 of Schedule 6 to the Planning Act 2008f1(“the Act”), and in accordance with Part 1 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011f2(“the 2011 Regulations”), for a change to the Walney Extension Offshore Wind Farm Order 2014f3(“the 2014 Order”) which is not a material change to the Order.
The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the 2011 Regulations, has determined to make an Order giving effect to the proposed change comprised in the application which in the opinion of the Secretary of State does not make any material change to the 2014 Order.
The Secretary of State, in exercise of the powers conferred by paragraphs 2(1) and (9) of Schedule 6 to the Act makes the following Order —
Annotations
Footnotes
- f1
-
2008 c.29. Paragraph 2 of Schedule 6 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c.23), by paragraph 72 of Schedule 13 and by Schedule 25 to the Localism Act 2011 (c.29), and by section 28 of the Infrastructure Act 2015 (c.7). There are other amendments which are not relevant to this Order.
- f2
-
S.I. 2011/2055. Part 1 was amended by S.I 2012/635 and S.I 2015/760.
- f3
-
S.I 2014/2950, as amended by S.I 2015/1270.