{
  "url": "https://openlegislation.uk/walney-extension-offshore-wind-farm-order-2014/schedule-1/paragraph-20",
  "json_url": "https://openlegislation.uk/walney-extension-offshore-wind-farm-order-2014/schedule-1/paragraph-20.json",
  "legislation": "uksi/2014/2950",
  "legislation_title": "The Walney Extension Offshore Wind Farm Order 2014",
  "legislation_url": "https://openlegislation.uk/walney-extension-offshore-wind-farm-order-2014",
  "path": "schedule/1/paragraph/20",
  "kind": "paragraph",
  "number": "20",
  "heading": "Highway accesses",
  "text": "(1) No stage of the connection works shall commence until written details of the siting, design, levels and layout of any new permanent or temporary means of access to a highway to be used by vehicular traffic, or any alteration to an existing means of access to a highway used by vehicular traffic, for that stage, has, after consultation with the highway authority, been submitted to and approved by the relevant planning authority. The written details submitted must be in accordance with the General Arrangement Drawings.\n(2) The highway accesses for each stage must be constructed in accordance with the approved details.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 Pt. 3 para. 20 in force at 28.11.2014, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2014/2950/schedule/1/paragraph/20",
    "retrieved_at": "2026-10-28T23:57:28.001582+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}