# The Walney Extension Offshore Wind Farm Order 2014, Paragraph 22: Public rights of way

Extent: E+W

(1) No stage of the connection works shall commence until a public rights of way diversion and closure scheme for that stage which accords with the principles of the Public Access Strategy, has, after consultation with the highway authority, been submitted to and approved by the relevant planning authority and that scheme shall include a programme for the temporary closure and re-opening of the public rights of way specified at Schedule 4 (public rights of way to be temporarily stopped up).
(2) Each stage of the connection works must be carried out in accordance with the approved scheme.

---