# The Walney Extension Offshore Wind Farm Order 2014, Paragraph 24: Surface and foul water drainage

Extent: E+W

(1) No stage of the connection works shall commence until for that stage written details of the surface and (if any) foul water drainage system (including means of pollution control) have, after consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the relevant planning authority.
(2) The surface and foul water drainage system for each stage must be constructed in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2014/2950/schedule/1/paragraph/24 (the official version)
Page: https://openlegislation.uk/walney-extension-offshore-wind-farm-order-2014/schedule-1/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.