# The Walney Extension Offshore Wind Farm Order 2014, Paragraph 28: Construction and environmental management plan

Extent: E+W

(1) No stage of the connection works shall commence until a construction and environmental management plan (CEMP) for that stage has been submitted to and approved by the relevant planning authority, in consultation with Natural England.
(2) The CEMP must be submitted to the relevant planning authority and Natural England at least four months prior to the commencement of the relevant stage of the connection works.
(3) The CEMP must cover all the subject areas set out in the certified CoCP and any other matters the relevant planning authority, having consulted with Natural England, reasonably requires.
(4) The CEMP for each stage must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2014/2950/schedule/1/paragraph/28 (the official version)
Page: https://openlegislation.uk/walney-extension-offshore-wind-farm-order-2014/schedule-1/paragraph-28
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.