# The Walney Extension Offshore Wind Farm Order 2014, Paragraph 3: Detailed offshore design parameters

Extent: E+W

(1) The total number of offshore substations forming part of the authorised development shall not exceed three.
(2) The dimensions of any offshore substation forming part of the authorised development (excluding any towers, helipads, masts and cranes) shall not exceed 75 metres in height when measured from LAT, 50 metres in length and 50 metres in width.

---