{
  "url": "https://openlegislation.uk/walney-extension-offshore-wind-farm-order-2014/schedule-1/paragraph-34",
  "json_url": "https://openlegislation.uk/walney-extension-offshore-wind-farm-order-2014/schedule-1/paragraph-34.json",
  "legislation": "uksi/2014/2950",
  "legislation_title": "The Walney Extension Offshore Wind Farm Order 2014",
  "legislation_url": "https://openlegislation.uk/walney-extension-offshore-wind-farm-order-2014",
  "path": "schedule/1/paragraph/34",
  "kind": "paragraph",
  "number": "34",
  "heading": "Control of noise during construction",
  "text": "(1) No stage of the connection works shall commence until a Construction Noise Management Plan (CNMP) for that stage has been submitted to and approved by the relevant planning authority.\n(2) The CNMP must set out the particulars of—\n(a) the construction works, and the method by which they are to be carried out;\n(b) the noise attenuation and mitigation measures to be taken to minimise noise resulting from the construction works, including any noise limits;\n(c) a scheme for monitoring the noise during the construction works to ensure compliance with the noise limits and effectiveness of the attenuation and mitigation measures.\n(3) The CNMP for each stage must be implemented as approved.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 Pt. 3 para. 34 in force at 28.11.2014, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2014/2950/schedule/1/paragraph/34",
    "retrieved_at": "2026-10-28T23:57:28.001582+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}