# The Walney Extension Offshore Wind Farm Order 2014, Paragraph 40: Onshore decommissioning

Extent: E+W

(1) Upon the cessation of commercial operation of the onshore substation comprised in Work No. 25, a written scheme for the demolition and removal of that substation, and the final proposed condition of the relevant land, including a proposed timetable, must be submitted to and approved by the relevant planning authority, in consultation with Natural England.
(2) The scheme for decommissioning shall be implemented as approved.

---