# The Walney Extension Offshore Wind Farm Order 2014, Paragraph 8: Detailed offshore design parameters

Extent: E+W

The total volume of cable protection (excluding cable crossings) included within Work No. 1(b) shall not exceed 27,000m³ with a maximum footprint of 35,000m².

---