# The Walney Extension Offshore Wind Farm Order 2014, Paragraph 9: Detailed offshore design parameters

Extent: E+W

The total volume of cable protection associated with cable crossings included within Work No. 1(b) shall not exceed 64,328m³ with a maximum footprint of 74,480m².

---
Source: https://www.legislation.gov.uk/uksi/2014/2950/schedule/1/paragraph/9 (the official version)
Page: https://openlegislation.uk/walney-extension-offshore-wind-farm-order-2014/schedule-1/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.