# The Walney Extension Offshore Wind Farm Order 2014, Paragraph 4: Design parameters for other deposits

Extent: E+W

(1) The total volume of scour protection for use with WTGs within Work No. 1 shall not exceed 2,277,000m³.
(2) The total volume of cable protection (excluding cable crossings) included within Work No. 1(b) shall not exceed 27,000m³ with a maximum footprint of 35,000m².
(3) The total volume of cable protection associated with cable crossings included within Work No. 1(b) shall not exceed 64,328m³. The total footprint of this cable protection shall not exceed 74,480m².

---