# The Warm Home Discount (Reconciliation) Regulations 2011, Regulation 9: Interim and final reconciliation: payments

Extent: E+W+S

(1) After the Operator carries out an interim reconciliation under Part 2 or a final reconciliation under Part 3, it must give notice—
(a) to each scheme electricity supplier which is liable to make or entitled to receive a payment, of—
(i) the amount of that payment (“the specified amount”); and
(ii) the supplier’s market share, as used in carrying out the reconciliation; and
(b) to each scheme electricity supplier which is liable to make a payment, of the date by which the payment is to be made, which must be not less than 3 working days from the date on which the notice is given;
(c) to each scheme electricity supplier which is entitled to receive a payment, of the date on which the payment is to be made, which must be not more than 10 working days after the date specified under sub-paragraph (b) (or if, under sub-paragraph (b), different dates are specified to different scheme electricity suppliers, not more than 10 working days after the latest of those dates).
(2) A scheme electricity supplier which is given a notice that it is liable to make a payment must pay the specified amount to the Operator by the date specified in the notice.
(3) The Operator must, subject to regulation 10(4), pay the specified amount to a scheme electricity supplier which is given a notice that it is entitled to receive a payment by the date specified in the notice.
(4) Where the Authority is the Operator, it must maintain a fund into which payments by scheme electricity suppliers and from which payments by the Operator under these Regulations are to be made.

---
Source: https://www.legislation.gov.uk/uksi/2011/1414/regulation/9 (the official version)