# The Water Resources (Control of Pollution) (Silage, Slurry and Agricultural Fuel Oil) (England) Regulations 2010, Paragraph 5

Extent: E+W

(1) Any facilities used for the temporary storage of slurry before it is transferred to a slurry storage tank must have adequate capacity to store—
(a) the maximum quantity of slurry that (disregarding any slurry which will be transferred directly into a slurry storage tank) is likely to be produced on the premises in any two day period; or
(b) a lesser capacity that the Agency agrees in writing is adequate to avoid any significant risk of pollution of controlled waters.
(2) Where slurry flows into a channel before discharging into a reception pit and the flow of slurry out of the channel is controlled by means of a sluice, the capacity of the reception pit must be adequate to hold the maximum quantity of slurry that can be released by opening the sluice.

---
Source: https://www.legislation.gov.uk/uksi/2010/639/schedule/2/paragraph/5 (the official version)
Page: https://openlegislation.uk/water-resources-control-of-pollution-silage-slurry-and-agricultural-fuel-oil-england-regulations-2010/schedule-2/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.