Every working standard capacity measure—

(a)

which is made of glass shall have been tested within 12 months before use;

(b)

which is made of metal and

(i)

is of 50 1 or less or 10 gal or less shall have been tested within 6 months before use;

(ii)

is of more than 50 1 or 10 gal shall have been tested within 24 months before use.