# The Welsh Water Authority (Ashgrove Treatment Works and Heronbridge to Sealand Pipeline and Associated Pipelines) Order 1988, Article 2: Power to acquire, continue and maintain works


(1) The Authority may acquire by agreement from the North West Water Authority and thereafter continue and maintain—
(a) the Ashgrove Treatment Works edged red on the deposited plan;
(b) the mains pipes and apparatus the approximate lines and positions of which are shown by blue and green lines on the deposited plan.

---
Source: https://www.legislation.gov.uk/uksi/1988/285/article/2 (the official version)
Page: https://openlegislation.uk/welsh-water-authority-ashgrove-treatment-works-and-heronbridge-to-sealand-pipeline-and-associated-pipelines-order-1988/article-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.