Introductory text
Infrastructure Planning
Made 21st October 2020
Coming into force 11th November 2020
The application was examined by a single appointed person appointed by the Secretary of State in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3.
The single appointed person, having considered the representations made and not withdrawn and the application together with the accompanying documents, in accordance with section 83 of the 2008 Act, has submitted a report and recommendation to the Secretary of State.
The Secretary of State, having considered the representations made and not withdrawn, and the report and recommendation of the single appointed person, has decided to make an Order granting development consent for the development described in the application with modifications which in the opinion of the Secretary of State do not make any substantial change to the proposals comprised in the application.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 140 of the 2008 Act, makes the following Order—
Annotations
Footnotes
- f1
-
2008 c.29. Sections 37, 83, 114 and 120 were amended by Localism Act 2011 (c.20). Section 115 was amended by the Localism Act 2011, the Housing and Planning Act 2016 (c.22) and the Wales Act 2017 (c.4).
- f2
-
S.I. 2009/2264, relevant amendments were made by S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, S.I. 2015/377, S.I. 2017/572; S.I. 2017/524 and S.I. 2020/764, and the instrument modified by S.I. 2012/1659.
- f3
-
S.I. 2010/103, as amended by S.I. 2012/635.