# The West Burton C (Gas Fired Generating Station) Order 2020, Paragraph 17: Protection of highway surfaces


(1) No stage of the authorised development must commence until details for undertaking condition surveys of the relevant highways which are maintainable at the public expense and which are to be used during construction of the authorised development have been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.
(2) The condition surveys must be undertaken in accordance with the approved details and a schedule of repairs, including a programme for undertaking any such repairs and their inspection, must, following the completion of the post-construction condition surveys, be submitted to and, after consultation with the highway authority, approved by the relevant planning authority.
(3) The schedule of repairs must be carried out as approved unless otherwise agreed with the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2020/1148/schedule/2/paragraph/17 (the official version)
Page: https://openlegislation.uk/west-burton-c-gas-fired-generating-station-order-2020/schedule-2/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.