Paragraph 3 Notice of commencement and completion of commissioning

Original text. Later amendments are not shown.

(1)

Notice of the intended commissioning of the authorised development must be given to the relevant planning authority, Nottinghamshire County Council, Lincolnshire County Council and West Lindsey District Council prior to such commencement and in any event not less than 7 days before the date that commissioning is commenced.

(2)

Notice of the intended completion of commissioning of the authorised development must be given to the relevant planning authority where practicable prior to such completion and in any event within 7 days from the date that commissioning is completed.