  "heading": "CORRECTIONS",
  "text": "Column (1)\nWhere the correction is made\nColumn (2)\nHow correction is made\nColumn (3)\nText substituted, inserted or omitted\nArticle 2(1) (interpretation), definition of “date of decommissioning”\nFor “phase” substitute\n“part”\nOmit\n“as approved under requirement 2 of Schedule 2 (requirements)”\nArticle 2(1), definition of “date of final commissioning”\nFor “approved” substitute\n“submitted”\nArticle 2 (interpretation)\nIn paragraph (3) for “includes” substitute\n“include”\nArticle 23 (private rights)\nIn Paragraph (1)(a), after “agreement”, insert\n“or through the grant of a lease of the land by agreement”\nIn paragraph (1)(a), before the final “or”, insert\n“;”\nArticle 31 (statutory undertakers)\nIn sub-paragraph (b), after “remove” insert\n“, relocate the rights of”\nArticle 38 (felling or lopping of trees and removal of hedgerows)\nIn paragraph (1), before sub-paragraph (a), insert\n“(a) obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development;”\nIn paragraph (2), for “paragraph (2)” substitute\n“paragraph (3)”\nIn paragraph (4), for “paragraph (2)” substitute\n“paragraph (3)”\nSchedule 2 (requirements), paragraph 1 (interpretation), (definition) of “relevant planning authority”\nIn sub-paragraph (a), omit\nparagraph (vi)\nIn sub-paragraph (b)(viii), for “Requirement 1”, substitute\n“Requirement 14”\nSchedule 2, paragraph 4 (community liaison group)\nIn sub-paragraph (3), for “approved” substitute\n“submitted”\nSchedule 2, paragraph 7 (landscape and ecological management plan)\nIn sub-paragraph (4), for “2(1)(h)” substitute\n“(h)”\nIn sub-paragraph (4), after “permitted preliminary works”, insert\n“as defined in article 2(1)”\nSchedule 2, paragraph 12 (archaeology)\nIn sub-paragraph (1)(c), for “improved” substitute\n“approved”\nIn sub-paragraph (2), for “sub-paragraph 1(c)”, substitute\n“sub-paragraph (1)(c)”\nSchedule 2, paragraph 17 (permissive path)\nIn sub-paragraph (2), for “365” substitute\n“364”\nSchedule 2, paragraph 21 (decommissioning and restoration)\nIn sub-paragraph (1), omit\n“as approved under requirement 2 of schedule 2 (requirements)”\nSchedule 2, paragraph 22 (long term flood risk mitigation)\nIn sub-paragraph (1), for “following consultation”, substitute\n“in consultation”\nSchedule 13 (documents and plans to be certified), Part 1 (documents and plans), row 2 (“book of reference”)\nIn column (2) (document reference), for “DEC/WB4.3”, substitute\n“EN010132/DEC/WB4.3”\nSchedule 13, Part 1, row 6 (“environmental statement appendix 9.12 biodiversity net gain report”)\nOmit\nthe entire row\nSchedule 13, Part 1, row 7 (“figure 8.18.3 landscape and ecological mitigation and enhancement measures West Burton 3 (Revision B)”)\nOmit\nthe entire row\nSchedule 13, Part 1, row 11 (“outline construction traffic management plan”)\nIn column (2) (document reference) for “EN010132/EX4/WB6.14.2”, substitute\n“EN010132/EX7/WB6.3.14.2”\nSchedule 13, Part 1, row 13 (“outline decommissioning statement”)\nIn column (2) (document reference), for “EN10132/EX6/WB7.14” , substitute\n“EN010132/DEC/WB7.2”\nIn column (3) (revision number), for “B”, substitute\n“C”\nIn column (4) (date), for “April 2024”, substitute\n“October 2024”\nSchedule 13, Part 1, row 17 (“outline operational environmental management plan”)\nIn column (2) (document reference), for “EN01032/EX5/WB7.14“, substitute\n“EN010132/DEC/WB7.14”\nIn column (3) (revision number), for “D”, substitute\n“E”\nIn column (4), for “April 2024”, substitute\n“October 2024”\nSchedule 13, Part 2 (substitute and supplementary documents), row 8 (technical note on cumulative effects of additional schemes)\nIn column (5) (examination library reference), for “[TBC]”, substitute\n“[REP7-016]”\nSchedule 13, Part 2\nAt the end of the table, insert a new row, and in column (1) (originating document), insert\n“Environmental Statement”\nin column (2) (replacement or supplementary part), insert\n“Environmental statement appendix 9.12 biodiversity net gain report”\nin column (3) (document reference), insert\n“EN010132/DEC/WB6.3.9.12_A”\nin column 4 (date), insert\n“November 2024”\nin column (5) (examination library reference), insert\n“N/A”\nSchedule 13, Part 2\nAt the end of the table, insert a new row, and in column (1) (originating document), insert\n“Environmental Statement”\nin column (2) (replacement or supplementary part), insert\n“Figure 8.18.3: Landscape and Ecology Mitigation and Enhancement Measures West Burton 3”\nin column (3) (document reference), insert\n“EN10132/DEC/6.4.8.18.3_B”\nin column (4) (date), insert\n“October 2024”\nin column (5) (examination library reference), insert\n“N/A”\nSchedule 15 (protective provisions), Part 3 (for the protection of National Grid Electricity Transmission Plc as electricity undertaker), paragraph 33 (notices)\nFor “article”, substitute\n“article 44”\nSchedule 15, Part 14 (for the protection of Uniper UK Limited), paragraph 192 (retained apparatus)\nFor “paragraph, 200”, substitute\n“paragraph 200”\nSchedule 15, Part 17 (for the protection of Tillbridge Solar Project Limited), paragraph 220\nFor ““Tillbridge Work No. [ ] Area” means the area for Work No. [ ] authorised in the Tillbridge Solar Order;”, substitute\n“Tillbridge Work No. 4E” means the area for Work No. 4E authorised in the Tillbridge Solar Order;”\nSchedule 15, Part 17 (for the protection of Tillbridge Solar Project Limited)\nFor “Tillbridge Work No. [] Area”, in each place it occurs, substitute\n“Tillbridge Work No. 4E”\nSchedule 15, Part 18 – For the Protection of EDF Energy (Thermal Generation) Limited, paragraph 240 (acquisition of land)\nIn sub-paragraph (1), in both places it appears, for “order”, substitute\n“Order”\nIn sub-paragraph (1), for “or the interest”, substitute\n“other interest”\nIn sub-paragraph (1), for “done”, substitute\n“than”\nIn sub-paragraph (1), at the end, insert\n“such agreement not to be unreasonably withheld”\nSchedule 15, Part 18 – For the Protection of EDF Energy (Thermal Generation) Limited, paragraph 250 (notices)\nFor “article”, substitute\n“article 44”",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/647/schedule/1",
    "retrieved_at": "2026-10-28T21:15:20.318504+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}