# The West Burton Solar Project Order 2025, Article 19: Compulsory acquisition of land

Extent: E+W

(1) The undertaker may acquire compulsorily so much of the Order land as is required for the authorised development or to facilitate, or as is incidental, to it.
(2) This article is subject to article 20 (time limit for exercise of authority to acquire land compulsorily), paragraph ‎(2) of article ‎22 (compulsory acquisition of rights), article 25 (acquisition of subsoil only), article 28 (rights under or over streets), article ‎29 (temporary use of land for constructing the authorised development), article ‎31 (statutory undertakers) and article 47 (Crown rights).

---
Source: https://www.legislation.gov.uk/uksi/2025/116/article/19 (the official version)
Page: https://openlegislation.uk/west-burton-solar-project-order-2025/article-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.