# The West Burton Solar Project Order 2025, Article 34: Benefit of the Order

Extent: E+W

(1) Subject to paragraph ‎(2) and article ‎35 (consent to transfer the benefit of the Order), the provisions of this Order have effect solely for the benefit of the undertaker.
(2) Paragraph ‎(1) does not apply to Work No. 4 in respect of which the provisions of this Order are for the benefit of the undertaker and National Grid.

---