  "url": "https://openlegislation.uk/west-burton-solar-project-order-2025/schedule-13/part-1",
  "json_url": "https://openlegislation.uk/west-burton-solar-project-order-2025/schedule-13/part-1.json",
  "legislation": "uksi/2025/116",
  "legislation_title": "The West Burton Solar Project Order 2025",
  "legislation_url": "https://openlegislation.uk/west-burton-solar-project-order-2025",
  "path": "schedule/13/part/1",
  "kind": "part",
  "number": "1",
  "heading": "DOCUMENTS AND PLANS",
  "text": "(1)\nDocument name\n(2)\nDocument reference\n(3)\nRevision number\n(4)\nDate\nAccess plan\nEN010132/EX5/WB2.5\nC\nApril 2024\nBook of reference\nEN010132/DEC/WB4.3\nG\nOctober 2024\nConcept design parameters and principles\nEN010132/EX5/WB7.13\nD\nApril 2024\nCrown land plan\nEN010132/APP/WB2.10\nA\nAugust 2023\nEnvironmental statement\nEN010132/APP/WB6.1\n1\nMarch 2023\n. . .\n. . .\n. . .\n. . .\n. . .\n. . .\n. . .\n. . .\nImportant hedgerows plan\nEN010132/EX4/WB2.9\nB\nFebruary 2024\nLand plan\nDEC/WB2.2\nE\nOctober 2024\nOutline battery storage safety management plan\nEN010132/EX6/WB7.9\nB\nApril 2024\nOutline construction environmental management plan\nEN010132/EX6/WB7.1\nD\nApril 2024\nOutline construction traffic management plan\nEN010132/EX7/WB6.3.14.2\nE\nMay 2024\nOutline decommissioning statement\nEN010132/DEC/WB7.2\nC\nOctober 2024\nOutline drainage strategy\nEN010132/APP/WB6.3.10.1\n1\nMarch 2023\nOutline ecological protection and mitigation strategy\nEN010132/APP/WB7.17\n1\nMarch 2023\nOutline landscape and ecological management plan\nDEC/WB7.3\nG\nOctober 2024\nOutline operational environmental management plan\nEN010132/DEC/WB7.14\nE\nOctober 2024\nOutline public rights of way management plan\nEN010132/EX5/WB6.3.14.3\nE\nApril 2024\nOutline skills, supply chain and employment plan\nEN010132/EX6/WB7.10\nB\nApril 2024\nOutline soil management plan\nEN010132/EX3/WB6.3.19.2\nA\nJanuary 2024\nPublic rights of way plan\nEN010132/EX4/WB2.4\nC\nFebruary 2024\nStreets plan\nEN010132/EX5/WB2.11\nD\nApril 2024\nWest Burton Power Station plan\nEN010132/EX6/WB8.2.11\n1\nApril 2024\nWorks plan\nDEC/WB2.3\nF\nOctober 2024\nWritten scheme of investigation\nEN010132/EX5/WB6.3.13.7\nB\nApril 2024",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Words in Sch. 13 Pt. 1 (including words in \"row 11\" and words in row 13 column 2) substituted (4.6.2025) by virtue of The West Burton Solar Project (Correction) Order 2025 (S.I. 2025/647), art. 1(1), Sch. 1 Table"
    },
    {
      "type": "F",
      "label": "F2",
      "text": "Words in Sch. 13 Pt. 1 omitted (4.6.2025) by virtue of The West Burton Solar Project (Correction) Order 2025 (S.I. 2025/647), art. 1(1), Sch. 1 Table"
    },
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 13 Pt. 1 in force at 15.2.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/116/schedule/13/part/1",
    "retrieved_at": "2026-10-28T21:20:55.440224+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}