# The West Burton Solar Project Order 2025, Paragraph 262: Arbitration

Extent: E+W

Any difference or dispute arising between the undertaker and UKAEA under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and UKAEA, be determined by arbitration in accordance with article ‎42 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2025/116/schedule/15/paragraph/262 (the official version)
Page: https://openlegislation.uk/west-burton-solar-project-order-2025/schedule-15/paragraph-262
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.