# The West Burton Solar Project Order 2025, Paragraph 75: Arbitration

Extent: E+W

Save for differences or disputes arising under paragraphs ‎67(2), ‎67(4), ‎68(1) and paragraph ‎69, any difference or dispute arising between the undertaker and Cadent under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and Cadent, be determined by arbitration in accordance with article ‎42 (arbitration) and in settling any difference or dispute, the arbitrator must have regard to the requirements of Cadent for ensuring the safety, economic and efficient operation of Cadent’s apparatus.

---