  "url": "https://openlegislation.uk/west-burton-solar-project-order-2025/schedule-2/paragraph-17",
  "json_url": "https://openlegislation.uk/west-burton-solar-project-order-2025/schedule-2/paragraph-17.json",
  "legislation": "uksi/2025/116",
  "legislation_title": "The West Burton Solar Project Order 2025",
  "legislation_url": "https://openlegislation.uk/west-burton-solar-project-order-2025",
  "path": "schedule/2/paragraph/17",
  "kind": "paragraph",
  "number": "17",
  "heading": "Permissive path",
  "text": "(1) Work No. 11 must be provided and open to the public prior to the date of final commissioning of the part of the authorised development that includes Work No. 1B.\n(2) The permissive path must be maintained and access by the public permitted for 364 days a year except where closure is required for maintenance or in an emergency until the date of decommissioning of the part of the authorised development that includes Work No. 1B.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Word in Sch. 2 para. 17(2) substituted (4.6.2025) by The West Burton Solar Project (Correction) Order 2025 (S.I. 2025/647), art. 1(1), Sch. 1 Table"
    },
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 17 in force at 15.2.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/116/schedule/2/paragraph/17",
    "retrieved_at": "2026-10-28T21:20:55.440224+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}