# The West Midlands Rail Freight Interchange Order 2020, Paragraph 6: Removal of apparatus


(1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or requires that the utility undertaker's apparatus is relocated or diverted, that apparatus must not be removed, diverted or otherwise altered under this Part of this Schedule, and/or any right of a utility undertaker to maintain apparatus in that land must not be extinguished, or made incapable of being exercised unless—
(a) it is in the reasonable opinion of the undertaker necessary for the purpose of carrying out the authorised development;
(b) any alternative, diverted or relocated apparatus required by the utility undertaker (acting reasonably) has been constructed and is in operation to the reasonable satisfaction of the utility undertaker in question in accordance with sub-paragraphs (2) to (6);
(c) any rights required by the utility undertaker (acting reasonably) including to install, access, retain, replace, divert, relocate and maintain any apparatus or alternative apparatus have been granted to the reasonable satisfaction of the utility undertaker; and
(d) any of the apparatus or alternative apparatus referred to in paragraph (b) or rights required and referred to in paragraph (c) do not in the reasonable opinion of the utility undertaker cause a material increase in the time, resources of and costs to the utility undertaker in using, operating or maintaining its apparatus unless agreed otherwise by the utility undertaker.
(2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal, diversion or alteration of any apparatus placed in that land, the undertaker must give to the utility undertaker in question 28 days' written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order an undertaker reasonably needs to remove any apparatus) the undertaker must, subject to sub-paragraph (3), afford to the utility undertaker the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus, and the utility undertaker may elect to leave in situ any apparatus that the undertaker requires to be removed provided that it permits the undertaker to remove the apparatus and at its own cost in place of the utility undertaker.
(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed the utility undertaker must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible use its best endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
(4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between the utility undertaker in question and the undertaker or in default of agreement settled by arbitration in accordance with article 47 (arbitration).
(5) The utility undertaker in question must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 47, and after the grant to the utility undertaker of any such facilities and rights as are referred to in sub-paragraphs (2) or (3), and in accordance with a timetable to be agreed with the undertaker (both parties acting reasonably) such timetable to have due and proper regard to the utility undertaker's statutory obligations with regard to its apparatus and undertaking including its obligation to maintain the supply of clean water at all times, proceed without unnecessary delay to construct and bring into operation the alternative apparatus and, subject to the provisions of sub-paragraph (2) of this paragraph, subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
(6) Regardless of anything in sub-paragraph (5), if the undertaker gives notice in writing to the utility undertaker in question that the undertaker desires itself to execute any work, or part of any work in connection with the construction or removal of apparatus in any land of the undertaker, that work, instead of being executed by the utility undertaker, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of the utility undertaker.
(7) Nothing in sub-paragraph (6) authorises the undertaker to execute the placing, installation, bedding, packing, removal, connection of disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is lain in a trench) within 300 millimetres of apparatus which is not being removed, diverted or altered without the consent of the utility undertaker (such consent not to be unreasonably withheld or delayed).

---
Source: https://www.legislation.gov.uk/uksi/2020/511/schedule/13/part/10/paragraph/6 (the official version)
Page: https://openlegislation.uk/west-midlands-rail-freight-interchange-order-2020/schedule-13/part-10/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.