# The West Midlands Rail Freight Interchange Order 2020, Paragraph 31: Interpretation


In this Part of this Schedule—
“rail terminal works” means the works required to construct and provide a rail terminal capable of handling at least four trains a day;
“rail terminal” means the rail terminal constructed as a result of and upon completion of the rail terminal works;
“rail provision milestones” means the actions, and the timing related thereto, set out in requirements 40 and 41 (rail provision milestones);
“undertaker” has the same meaning as sub-paragraph (a) of the definition of “undertaker” in article 2 (interpretation); and
“GRIP 3”, “GRIP 4” and “GRIP 5” relate to Network Rail's Governance for Rail Investment Projects current at the date of this order.

---
Source: https://www.legislation.gov.uk/uksi/2020/511/schedule/2/paragraph/31 (the official version)
Page: https://openlegislation.uk/west-midlands-rail-freight-interchange-order-2020/schedule-2/paragraph-31
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.