# The West of Scotland Water Authority (Lochranza – Allt Easan Biorach) Water Order 1999, Schedule 1


The works referred to in this Order and shown on the deposited plan are–
Work No. 1
An intake structure located at National Grid Reference NR 94414972.
Work No. 2
A raw water main from the intake on the Allt Easan Biorach to the new Treatment Works via the gauge at Work No. 3.
Work No. 3
A gauge to measure and record the amount of water taken from the river and the rate at which the said amount was taken located at national Grid Reference NR 94264989.
Work No. 4
A discharge pipe from the works located at National Grid Reference NR 94274992.

---