Paragraph 13 Combined heat and power
Within 12 months of ceasing to supply heat and/or power to the Kemsley Paper Mill, the undertaker must submit to the relevant planning authority for its approval a strategy (“the CHP strategy”).
The CHP strategy submitted and approved must—
consider the opportunities that reasonably exist at the time of submission for the export of heat and/or power from the K3 Generating Station to other users; and
include a list of actions (if any) that the undertaker is reasonably to take (without material additional cost to the undertaker) to increase the potential for the export of heat from the K3 Generating Station to other users.
The undertaker must take such actions as are included, within the timescales specified, in the approved CHP strategy.